What you type
The readings, the tariff and the target are worked out in the page you have open. They are not saved and they are not sent anywhere. The page counts visits, as every page of ours does; the count holds no figures you type.
How each figure is worked out
PUE
Total facility energy divided by IT equipment energy, rounded to two decimals; an exact half goes to the even figure, so Case A’s 1.705 reads 1.70, as the task force prints it.
Everything else
The total less the IT energy: cooling, power losses, lighting and the rest.
Rupees
Everything else in kWh, times the tariff you type.
Carbon
kWh times the grid factor, divided by 1,000: tonnes of CO2.
A target
The same IT energy at the target PUE; the difference from your total is what it would save.
If something is wrong
Tell us what you saw and on which page; we will check it against the source and correct it.